The Grand Vertical — Site Progress

Choose a section to open

V4 Bussiness Centre — Dashboard

as of Friday, 07 August 2026
Overall completion
0.0 %
work value done 0 of 51 Cr
Manpower (06 Aug)
0
Concrete poured to date
0 Cu.Mtr
Days reported
5

BOQ Completion

cumulative work done vs BOQ quantity
BOQ completion
0.0 %
Items in progress
0 of 45
Value of work done
0
Value remaining
51 Cr
Water Bore Well (2” Dia up to 350 ft Deep)V-4 Preliminary Works BOQ · Preliminary Works
0 / 1 Job
0%
Levelling and Dressing of Site AreaV-4 Preliminary Works BOQ · Preliminary Works
0 / 1 Job
0%
Removing and Disposing of Surplus/Excavated Material From SiteV-4 Preliminary Works BOQ · Preliminary Works
0 / 1 Job
0%
Electrical Room + Temporary Toilets WorkV-4 Preliminary Works BOQ · Preliminary Works
0 / 1 Job
0%
Temporary Site Office Setup WorkV-4 Preliminary Works BOQ · Preliminary Works
0 / 1 Job
0%
Installation of Water Sprinkling SystemV-4 Preliminary Works BOQ · Preliminary Works
0 / 1 Job
0%
…and 39 more items — click “Show all” or pick a BOQ Name above.
Total poured to date
0
0 pour(s)
This month (Aug)
0
Poured on 07 Aug
0
Suppliers used
0

Concrete Poured — Last 14 Days

No concrete poured in the last 14 days

Concrete Summary

filter wise
No concrete recorded yet — entries appear here grouped segment / supplier / floor / item / PSI wise.

Concrete Summary Matrix

Supplier × Design Mix — like your Excel summary Filters:
No concrete pours match the selected filters.

Manpower — Last 14 Days

No manpower recorded in the last 14 days

Recent Daily Reports

DateSummaryMP
06 Augno activities listed
05 Augno activities listed
04 Augno activities listed
03 Augno activities listed
02 Augno activities listed
DPR-007
set start date
32

Daily Progress Sheet — Fri, 07 Aug 2026

measured work done vs BOQ
Day forms:
S.NoItem DescriptionFloor BOQ - QtyUnit NoLengthBreadthHeight =Quantity Cumulative%
1
Piles Drilling Work
↳ Piling Work BOQ - Labour
Piling 27,380.25 RUNNING FOOT-RFT 2 = 2 482 / 27,380.25
1.8%
2
Steel Fixing For Piles — Material
↳ Piling Work BOQ - Material
Piling 612,240.77 Kilogram-KG 2 1,986 = 3,972 13,902 / 612,240.77
2.3%
3
Concrete Pouring of Piles (4000 Psi) — Material
↳ Piling Work BOQ - Material
Piling 3,654.24 Cubic meter-M3 2 0.46 26.6 = 24.31 85.09 / 3,654.24
2.3%
4
Steel Fixing For Piles — Labour
↳ Piling Work BOQ - Labour
Piling 612,240.77 Kilogram-KG 2 1,986 = 3,972 13,902 / 612,240.77
2.3%
5
Concrete Pouring of Piles (4000 Psi) — Labour
↳ Piling Work BOQ - Labour
Piling 3,654.24 Cubic meter-M3 2 0.46 26.6 = 24.31 85.09 / 3,654.24
2.3%

Activity Sheet — Fri, 07 Aug 2026

work carried out at site
Day forms:
4 activities on Fri, 07 Aug 2026 — click 07 Aug above or + Add Activity to open & edit.
#Activity descriptionLocation
1Drilling of Piles111-120
2Fabrication of Pile Cage111-120
3Steel Fixing of pile111-120
4concrete of Piles111-120

Man Power — Fri, 07 Aug 2026

nos deployed on this day Total: 32
Day forms:
Man Power — Contractor (19)
RoleNos
Steel Fixer6
Misc6
Site Engineer2
Rig Operator2
Surveyor1
Welder1
Crane Operator1
Man Power — Vertical (13)
RoleNos
Guard4
Project Manager1
Construction Manager1
Site Engineer1
Surveyor1
Quantity Surveyor1
Electrician1
Office Boy1
Store in charge1
Store Helper1
TOTAL MANPOWER (Contractor + Vertical): 32

Last 7 Reported Days

daily totals
DateTop rolesTotal
Thu, 06 Aug 2026C:19 · V:13 · Steel Fixer 6 · Misc 6 · Guard 432
Wed, 05 Aug 2026C:19 · V:13 · Steel Fixer 6 · Misc 6 · Guard 432
Tue, 04 Aug 2026C:20 · V:12 · Steel Fixer 6 · Misc 6 · Guard 432
Mon, 03 Aug 2026C:13 · V:12 · Misc 6 · Guard 4 · Site Engineer 325
Sun, 02 Aug 2026C:12 · V:22 · Store in charge 11 · Misc 6 · Guard 434
Sat, 01 Aug 2026C:14 · V:12 · Misc 6 · Guard 4 · Crane Operator 326

Concrete Record — Fri, 07 Aug 2026

pours on this day
Day forms:
Item / WorkFloorDesign Mix SegmentVendorTM # Slip #Slip PicUnitQty
Concrete Pouring of Piles (4000 Psi)Piling Work Material4000 PsiPilesBrightech6730741Cubic meter-M315
Concrete Pouring of Piles (4000 Psi)Piling Work Material4000 PsiPilesBrightech9562742Cubic meter-M310

Concrete History

all recorded pours — search below Total: 0

Daily Pics — Fri, 07 Aug 2026

up to 6 photos — shown on DPR
Day forms:

Photo Log

days with photos

Concrete Detail Report

as of Sunday, 02 August 2026
Total concrete poured
0 Cu.Mtr
This month
0 Cu.Mtr
Total pours
0
Suppliers
0 · 0 mixes
No concrete recorded yet — entries appear here Supplier / PSI / Segment wise.
DPR Date: Page size is A3 portrait — choose A3 in the print dialog (destination “Save as PDF” to get a PDF file).
Report Month: Page size is A3 landscape — pick A3 + Landscape in the print dialog (destination “Save as PDF” for a PDF). The dashed boxes are yours to type in; they save automatically.

Work Plan & Progress

planned schedule vs actual — as of the selected date

Paste rows with a header row containing Item, Start Date and Duration (or End Date). Matched to BOQ items by name.

View:
BOQ GroupItemsBOQ ValueDone Value% CompleteSPI

SPI Breakdown — where the number comes from

SNoWBSGrandParentName/BOQItemNameUOMQtyQty Planned in This PeriodStart DateEnd DateDurationWORK DONE%age of Work DoneSPIStatus

This sheet is filled by ⬆ Import Plan (not typed here). Use ⬇ Export Plan to get the template, fill Planned Qty / Start Date / Duration in Excel, then Import back. End, % (vs Planned Qty) & Status come from your daily progress. SPI per item = Earned Qty ÷ Planned-Qty-to-date; the group/overall SPI is weighted by planned value (correct across mixed units like m³, tons, m²). Press 💾 SAVE to store.

Executive Dashboard

Plant Concrete Vs Actual Concrete

Plant = Ready-Mix entries · Actual = Progress / Measurement · one row per item on its Material BOQ line · measured volume counted once (Material or Labour, not both)
Total Plant Concrete
0 Cu.Mtr
Total Actual Concrete
0 Cu.Mtr
Difference (Plant − Actual)
0 Cu.Mtr
Overall Waste %
% (Plant−Actual)/Plant
Filter: From to 0 rows · Plant 0 · Actual 0
DateItem DescriptionSub SegmentFloor BOQ Qty TotalPlant ConcActual Concrete Diff (Plant−Actual)Waste %Cumulative PlantCumulative Actual
No concrete records for this selection.

Project Information

appears in the DPR header Read-only

BOQ Items

imported — read-only here; progress is tracked against these
BOQ items
45
Total BOQ cost
51 Cr
Value of work done
1.67 Cr
Value remaining
49.33 Cr

Paste the BOQ rows with the header — column order: S.No · WBS Group/BOQ Name (col B) · Sub Parent (col C) · Floor · Item Name · UOM · Qty · Rate.

S.NoWBS Group / BOQ NameSub Parent / SegmentItem DescriptionFloor / Section UnitBOQ QtyRate BOQ ValueDone (cum.)
1 V-4 Preliminary Works BOQ Preliminary Works Water Bore Well (2” Dia up to 350 ft Deep)Preliminary Works Job 1 280,000 280,000 0 / 1
2 V-4 Preliminary Works BOQ Preliminary Works Levelling and Dressing of Site AreaPreliminary Works Job 1 45,000 45,000 0 / 1
3 V-4 Preliminary Works BOQ Preliminary Works Removing and Disposing of Surplus/Excavated Material From SitePreliminary Works Job 1 250,000 250,000 0 / 1
4 V-4 Preliminary Works BOQ Preliminary Works Electrical Room + Temporary Toilets WorkPreliminary Works Job 1 966,108.46 966,108.46 0 / 1
5 V-4 Preliminary Works BOQ Preliminary Works Temporary Site Office Setup WorkPreliminary Works Job 1 300,000 300,000 0 / 1
6 V-4 Preliminary Works BOQ Preliminary Works Installation of Water Sprinkling SystemPreliminary Works Job 1 350,000 350,000 0 / 1
7 V-4 Preliminary Works BOQ Preliminary Works Installation of Poles (8 ft) & Light FixturesPreliminary Works Job 1 1,434,000 1,434,000 0 / 1
8 V-4 Preliminary Works BOQ Preliminary Works Installation of Diesel GeneratorPreliminary Works Number-No 1 2,000,000 2,000,000 0 / 1
9 V-4 Preliminary Works BOQ Preliminary Works Site Fencing, Branding & Signage WorksPreliminary Works Job 1 1,350,000 1,350,000 0 / 1
10 V-4 Preliminary Works BOQ Preliminary Works Wapda Connection ChargesPreliminary Works Job 1 6,000,000 6,000,000 0 / 1
11 V-4 Preliminary Works BOQ Preliminary Works Miscellaenous Works Cost For Preliminary WorksPreliminary Works Job 1 500,000 500,000 0 / 1
12 V-4 Tubewell Work BOQ Tubewell Installation Work Preliminary Works for Tubewell InstallationTubewell Installation Work Job 1 575,000 575,000 0 / 1
13 V-4 Tubewell Work BOQ Tubewell Installation Work Tubewell Installation - 01Tubewell Installation Work Job 1 2,823,250 2,823,250 1 / 1
14 V-4 Tubewell Work BOQ Tubewell Installation Work Tubewell Installation - 02Tubewell Installation Work Job 1 2,823,250 2,823,250 1 / 1
15 V-4 Tubewell Work BOQ Tubewell Installation Work Tubewell Installation - 03Tubewell Installation Work Job 1 2,823,250 2,823,250 1 / 1
16 V-4 Tubewell Work BOQ Tubewell Installation Work Recharge Well Bore InstallationTubewell Installation Work Job 1 1,200,000 1,200,000 1 / 1
17 V-4 Tubewell Work BOQ Tubewell Installation Work Miscellaenous Works Cost For TubewellTubewell Installation Work Job 1 200,000 200,000 0 / 1
18 V-4 Tubewell Work BOQ Tubewell Installation Work Vo # 01 Misc WorksTubewell Installation Work Job 1 300,000 300,000 0 / 1
19 V-4 Piling Work BOQ Piling Work BOQ - Material Steel Fixing For PilesPiling Kilogram-KG 612,240.77 265 162,243,804.05 13,902 / 612,240.77
20 V-4 Piling Work BOQ Piling Work BOQ - Material Concrete Pouring of Piles (4000 Psi)Piling Cubic meter-M3 3,654.24 28,724.43 104,965,961.08 85.09 / 3,654.24
21 V-4 Piling Work BOQ Piling Work BOQ - Material Concrete Pouring of Capping Beam (5000 Psi)Piling Cubic meter-M3 459.34 35,914.29 16,496,950.19 0 / 459.34
22 V-4 Piling Work BOQ Piling Work BOQ - Material Steel Fixing For Capping BeamPiling Kilogram-KG 53,867.54 265 14,274,898.1 0 / 53,867.54
23 V-4 Piling Work BOQ Piling Work BOQ - Material Concrete Pouring of Waller Beam (5000 Psi)Piling Cubic meter-M3 357.08 35,914.29 12,824,274.67 0 / 357.08
24 V-4 Piling Work BOQ Piling Work BOQ - Material Steel Fixing For Waller BeamPiling Kilogram-KG 74,708.2 265 19,797,673 0 / 74,708.2
25 V-4 Piling Work BOQ Piling Work BOQ - Material Binding WirePiling Kilogram-KG 8,922.91 330 2,944,561.2 0 / 8,922.91
26 V-4 Piling Work BOQ Piling Work BOQ - Material Blind Concrete 1500 Psi Under Capping BeamPiling Cubic meter-M3 40.71 12,000 488,560.2 0 / 40.71
27 V-4 Piling Work BOQ Piling Work BOQ - Material Miscellaneous Work Cost for Piling & Beams WorkPiling Job 1 5,217,673.36 5,217,673.36 0 / 1
28 V-4 Piling Work BOQ Piling Work BOQ - Labour Mobilization of Piling Rig and Associated EquipmentPiling Job 1 380,000 380,000 1 / 1
29 V-4 Piling Work BOQ Piling Work BOQ - Labour Piles Drilling WorkPiling RUNNING FOOT-RFT 27,380.25 646 17,687,641.5 482 / 27,380.25
30 V-4 Piling Work BOQ Piling Work BOQ - Labour King Post Piles Drilling WorkPiling RUNNING FOOT-RFT 1,092.5 646 705,755 0 / 1,092.5
31 V-4 Piling Work BOQ Piling Work BOQ - Labour Wet Drilling Work (2.5 ft dia)Piling Job 1 1,000 1,000 0 / 1
32 V-4 Piling Work BOQ Piling Work BOQ - Labour Steel Fixing For PilesPiling Kilogram-KG 612,240.77 7.12 4,359,154.28 13,902 / 612,240.77
33 V-4 Piling Work BOQ Piling Work BOQ - Labour Concrete Pouring of Piles (4000 Psi)Piling Cubic meter-M3 3,654.24 847.54 3,097,114.57 85.09 / 3,654.24
34 V-4 Piling Work BOQ Piling Work BOQ - Labour Excavation, Dressing, Levelling and Compaction for Capping BeamPiling Cubic foot-FT3 16,221.21 29 470,415.16 0 / 16,221.21
35 V-4 Piling Work BOQ Piling Work BOQ - Labour Concrete Pouring of Capping Beam (5000 Psi)Piling Cubic meter-M3 459.34 6,709.66 3,082,030.38 0 / 459.34
36 V-4 Piling Work BOQ Piling Work BOQ - Labour Steel Fixing For Capping BeamPiling Kilogram-KG 53,867.54 7.6 409,393.3 0 / 53,867.54
37 V-4 Piling Work BOQ Piling Work BOQ - Labour Drill and Grout of Steel Bars into Piles for Waller BeamPiling Number-No 2,264 2,660 6,022,240 0 / 2,264
38 V-4 Piling Work BOQ Piling Work BOQ - Labour Excavation, Dressing, Levelling and Compaction for Waller BeamPiling Cubic foot-FT3 12,610.08 19 239,591.6 0 / 12,610.08
39 V-4 Piling Work BOQ Piling Work BOQ - Labour Concrete Pouring of Waller Beam (5000 Psi)Piling Cubic meter-M3 357.08 7,380.63 2,635,475.36 0 / 357.08
40 V-4 Piling Work BOQ Piling Work BOQ - Labour Steel Fixing For Waller BeamPiling Kilogram-KG 74,708.2 9.5 709,727.9 0 / 74,708.2
41 V-4 Piling Work BOQ Piling Work BOQ - Labour Installation of MS Struts with Base Plates (48" Dia Pipe)Piling Kilogram-KG 248,399 295 73,277,705 0 / 248,399
42 V-4 Piling Work BOQ Piling Work BOQ - Labour Removal & Re-Installation of Struts (Layer-01 to Layer-02Piling Kilogram-KG 72,000 75 5,400,000 0 / 72,000
43 V-4 Piling Work BOQ Piling Work BOQ - Labour Excavation Upto Foundation LevelPiling Cubic foot-FT3 3,691,890 2 7,383,780 0 / 3,691,890
44 V-4 Piling Work BOQ Piling Work BOQ - Labour Shotcrete on Pile Face (2" thick with Welded Wire Mesh) - 3000 PsiPiling Square foot-FT2 27,427 750 20,570,250 0 / 27,427
45 V-4 Piling Work BOQ Piling Work BOQ - Labour Blind Concrete 1500 Psi Under Capping BeamPiling Cubic meter-M3 40.71 1,332.77 54,261.68 0 / 40.71
TOTAL BOQ COST 509,959,750.05

BOQ quantities and rates can only be changed by importing again — import matches items by name, so recorded progress is kept.

Manpower Roles

the roles shown on the man power sheet
Project ManagerConstruction ManagerSite EngineerSurveyorQuantity SurveyorQA/QCSafety EngineerLab TechnicianElectricianMechanicPlumberWelderDriverCookOffice BoyMasonCoolieSteel FixerCarpenterScaffolderGuardCrane OperatorMiscRig OperatorStore in chargeStore Helper

Concrete Segments

dropdown options for the Segment column
ColumnSlabBeamCapping BeamWaller BeamRaftFootingWallPilesLift Core

Concrete Vendors

dropdown options for the Vendor column
BrightechTetraD-Mix

Users & Login

who can sign in — admins can edit, viewers can only view
User NameEmailRolePassword

Passwords are stored on this computer only. The signed-in Admin can add or remove users and change roles.

Data Backup

All data is saved automatically in this browser on this computer. Export a backup regularly (e.g. weekly) to keep your records safe or to move them to another computer. To restore a backup, use the ⬆ Import Data button at the top (your password required).

Sharing with another person? Use 📤 Save shareable App — it creates an HTML file with all current users, BOQ and records built in, so when they open it nothing is missing. (A plain copy of this file opens empty on their computer, because data lives in the browser, not in the file.)

This software is developed by Omer Mehmood

💾 Progress saved ✓